Treasure Cay Is Being Priced on a Sale That Hasn't Closed Yet

November 12, 2026

Eric Bethel owns condominiums in Treasure Cay. His renters keep asking him about the redevelopment. Several of them, he told The Tribune in October, had been "kind of waiting to see what happened with the sale" before buying or building on the island. He expects them to "pull the trigger" once it goes through.

That waiting room explains the Treasure Cay market this winter. Jacksonville-based GreenPointe Holdings agreed to buy and redevelop the resort from the Meister family's Treasure Cay Ltd. The $177 million plan is still in its closing stage. Owners near Treasure Cay Beach already report that their property values have risen sharply ahead of it. A large share of the money behind the plan is meant to come from outside investors and from people who buy in before anything is built. For a buyer looking at a Bahama Beach Club condo or a nearby villa, the useful question is how much of the asking price depends on that plan.

The first place in line is a boat slip

The first thing GreenPointe has put up for sale is a marina slip, not a condo. Its "marina founders" programme, quoted by Tribune Business, offers 47 Phase One slips in Treasure Cay harbour. The materials put the slips at less than half the price of recent comparable slip sales in the region, for vessels from 50 to 120 feet and beyond.

The programme materials also set the order in which future homes will be offered:

"Founding marina owners receive priority selection for future Treasure Cay real estate offerings, based on the order in which slip contracts are received."

So the first pick of new homes goes to boat owners, in the order their slip contracts come in. A buyer who wants a new-build home in the redeveloped Treasure Cay, rather than a resale condo, will be choosing after everyone who signed a slip contract first. The same materials promise "the return of the iconic Tipsy Seagull Bar & Grille" and a "future Marina Village." Those are the details that make a slip contract an early ticket to the rest of the project.

The slips help pay for the plan they are queuing for

The early sales do more than reward early buyers. In 2025, Tribune Business reported on a GreenPointe offering memorandum that set a $121.406 million budget for the first two years of work. About $65 million, or 53.5 percent, was to be equity. GreenPointe planned to put in $5 million of its own funds and raise the rest of that equity from other investors. The balance of the budget was to come from residential real estate sales, marina slip sales and operating revenue from the Treasure Cay club.

Here is how that document planned to spend the money:

Line item in the 2025 offering memorandum Planned spend
Acquisition $25 million
Master infrastructure $18.943 million
Residential infrastructure $12.59 million
Marina construction just over $20 million
Golf and racquet club $14.131 million
Marina village and beach club, first phase $12.851 million
Soft costs and contingency the balance

The marina, about $20 million of the budget, is being sold partly to pay for itself. The residential sales the plan counts on also sit behind the slip queue. A resale owner near the beach benefits if every step goes through. The buyer of that resale condo is paying today for a sequence in which each stage is partly funded by sales made at the stage before it.

Permitted, pending and projected

Treasure Cay has had a reasonable claim to "imminent" for a long time. Each part of the project is at a different stage, and the dates show it:

  1. September 2024. The Davis administration and GreenPointe principal Edward Burr signed a Heads of Agreement. The government's release described a $177 million first phase covering restoration of the marina and harbour, new residential units, a hotel and a grocery store.
  2. The original projections. GreenPointe's September 2024 announcement expected groundbreaking in 2025 and a first-phase opening in 2027. It estimated about $1.5 billion of investment at full build-out and planned a 175-slip marina. Later plans call for 163 slips.
  3. Summer 2025. GreenPointe told Treasure Cay homeowners it aimed to have all permits and approvals by October 2025.
  4. October 2026. Bahamas Investment Authority director Phylicia Woods-Hanna told Tribune Business that pre-construction and demolition permits had been issued and that the parties were "working through the final check-list of closing items."
  5. October 21, 2026. The Tribune's follow-up still described the sale as being worked through to completion.

Bill McLean heads the Beach Villas Owners Association, which has about 120 members and is the largest homeowners group on Treasure Cay. He explained to Tribune Business why closing is slow: the deal "includes dozens and dozens and dozens of individual land parcels," each needing title work. He also told the paper that existing Beach Villas and Treasure Cay owners have seen "very significant" increases in property values, with demand "very high even before GreenPointe is able to offer any real estate for sale excluding boat slips." Daphne DeGregory-Miaoulis, immediate past president of the Abaco Chamber of Commerce, was more cautious in the same Tribune Business report. The outlook "sounds more positive than it has done in the past," she said, "but I am still not going to the bank on it."

Abaco buyers are already pricing in the risk

Owners say Treasure Cay values are up sharply, but no public figure puts a number on Treasure Cay by itself. The closest data covers all of Abaco. In a brokerage analysis of Bahamas MLS data for the third quarter of 2026, reported by Tribune Business, Abaco stood out in three ways:

  • More signed deals. Abaco was the main market among the five major islands where contracted home sales rose over the same quarter of 2025.
  • Fewer finished ones. Completed home sales in Abaco fell year over year. Home prices were above last year but lower than in the second quarter of 2026.
  • The biggest discount from asking. Sellers on New Providence, Eleuthera, Exuma and Grand Bahama all got more than 90 percent of their asking price in the quarter. Abaco sellers got about 88 percent, the lowest of the five.

Abaco land was weaker across the board in the same quarter, with fewer new listings, contracted sales and completed sales, and land prices below the prior year.

Taken together, buyers are interested in Abaco, and Abaco sellers give up more at the table than sellers anywhere else in the country. In Treasure Cay, that gap between asking and achieved price is where the redevelopment gets negotiated. A seller can point to issued permits and the slip programme. A buyer can point to a 2027 opening that was projected back in 2024, with the sale still closing and construction still ahead.

What owning there looks like this December

A buyer who closes this winter owns in the Treasure Cay that exists now, not the one in the renderings, and that version runs on a seasonal schedule. According to the Abaco Sun's fall 2026 closures list, Bahama Beach Club's Pavilion restaurant was set to reopen in mid-December. Treasure Sands Club planned a holiday-menu run from November 24 to December 2, another closure from December 3 to 22, and a season reopening on December 23. Coops Waterfront Bar & Grill and Sunset Pizza were scheduled to reopen in October.

Errands are the other part of the picture. Dan Proctor, a second-home owner in Abaco for more than 25 years, told The Tribune that services in Marsh Harbour are about 30 minutes away over roads that are sometimes in poor condition. The commercial center promised in GreenPointe's 2024 plan, with a grocery store, hardware store, bank and business offices, would close much of that gap. It is also part of the project that has not been built yet.

Getting there has its own wait. In October 2025, The Tribune described Treasure Cay International Airport with no terminal, a plastic shed as the waiting area, and Customs and Immigration working from trailers. The Abaco Sun's September 2026 airline guide says the airport currently takes only smaller planes, while most commercial traffic uses Marsh Harbour, about 45 minutes south. Aztec Airways lists scheduled Treasure Cay service on Sundays, Wednesdays and Fridays. A buyer whose plans depend on easy flights should look at these schedules as closely as at the floor plan.

FAQ

Has the Treasure Cay sale to GreenPointe closed? In its October 21, 2026 coverage, The Tribune described the Meister family and GreenPointe as still working through final closing items, with pre-construction and demolition permits already issued.

What is planned for the redevelopment? Reported plans include a new 163-slip marina, a marina village with shops and dining, the return of the Tipsy Seagull Bar & Grille, a new Coco Beach Bar, a rebuilt golf course and racquet facilities for tennis, pickleball and padel, and a wastewater treatment plant. Medical care and a grocery store are being explored.

Does buying a resale condo now put me in line for new GreenPointe homes? Under the founders programme as reported, priority for future Treasure Cay real estate goes to marina founders in the order their slip contracts are received.